DG Installation
Turnkey acoustic and low side execution for one of Bangalore's largest financial campus DG installations.
Goldman Sachs Techpark
Bangalore
Challenge
A mission-critical financial campus requiring eight high-capacity DG sets with strict noise compliance, coordinated ventilation, and uninterrupted power infrastructure across a dense tech park environment.
Solution
OPTIMA executed complete DG room acoustics, ventilation design, exhaust routing, and low side electrical integration for all eight 2500 kVA units with phased commissioning to avoid operational disruption.
Outcome
Delivered a fully compliant, acoustically treated power facility supporting 24/7 operations with measurable noise reduction and reliable multi-DG coordination.